Feb. 1, 2013

HADLEY, Mass. - Construction continues at the Northampton site, and the framing of the boathouse is nearing completion. The roof beams have been fully installed and there are palates of flooring material on location waiting to be installed.

The front wall, which faces the Connecticut River, is also nearing completion, and the framing for the bay doors has begun.

To view this week's progress, a photogallery can be accessed here.

 

 